Stage Number Update | Status Titles Anticipated Documentation
Stage 21 Titles received Titles received

Plan of Subdivision

Memorandum of Common Provisions

Engineering

Compaction Report

Final Lot Pegging

Stage 22 Titles received Titles received

Plan of Subdivision

Memorandum of Common Provisions

Engineering

Compaction Report

Final Lot Pegging

Stage 23 Statement of compliance received April - May 2017

Plan of Subdivision

Memorandum of Common Provisions

Engineering

Stage 24 Statement of compliance received April - May 2017

Plan of Subdivision

Memorandum of Common Provisions

Engineering

Stage 25 Kerbing complete - Awaiting PC May - June 2017

Plan of Subdivision

Memorandum of Common Provisions

Engineering

Stage 26 Kerbing complete - Awaiting PC May - July 2017

Plan of Subdivision

Memorandum of Common Provisions

Engineering

 