22 Jan 2025
Communities in Western Australia
Aarya, Piara Waters
Stage | Titles Due | PC Due | Water Access | Energisation Due | Pegging Due | Guided Access |
---|---|---|---|---|---|---|
001 | Oct - Nov '25 | Jul '25 | Sep '25 | Nov '25 | Jul '25 | Jul '25 |
01A | Oct - Nov '25 | Jul '25 | Sep '25 | Nov '25 | Jul '25 | Jul '25 |
Allara, Eglinton
Stage | Titles Due | PC Due | Water Access | Energisation Due | Pegging Due | Guided Access |
---|---|---|---|---|---|---|
011 | Titled | Achieved | Achieved | Achieved | Complete | Complete |
016 | Titled | Achieved | Achieved | Jan '25 | Complete | Open Access |
017 | Titled | Achieved | Jan '25 | Mar '25 | Nov '24 | Open Access |
020 | Mar - Apr '25 | Feb '25 | Apr '25 | Jun '25 | Feb '25 | Feb '25 |
021 | Jun - Aug '25 | May '25 | Jul '25 | Sep '25 | May '25 | May '25 |
Cassia, Kwinana
Stage | Titles Due | PC Due | Water Access | Energisation Due | Pegging Due | Guided Access |
---|---|---|---|---|---|---|
Cassia Glades | ||||||
003 | Jan '25 | Achieved | Achieved | Achieved | Mar '25 | |
004 | Mar - May '25 | Mar '25 | May '25 | Jul '25 | Mar '25 | Mar '25 |
Cassia Rise | ||||||
004 | Jan '25 | Feb '25 | Mar '25 | May '25 | Jan '25 | |
05A | Mar - May '25 | Mar '25 | May '25 | Jul '25 | Mar '25 | |
05B | Jun - Jul '25 | Jun '25 | Aug '25 | Oct '25 | Jun '25 |
Catalina, Mindarie & Clarkson
Stage | Titles Due | PC Due | Water Access | Energisation Due | Pegging Due | Guided Access |
---|---|---|---|---|---|---|
Catalina Beach | ||||||
033 | June 2025 | May '25 | Jul '25 | Sep '25 | May '25 | May '25 |
034 | June - July '25 | May '25 | Jul '25 | Sep '25 | May '25 | |
Catalina Green | ||||||
039 | Titled | Achieved | Feb '25 | Feb '25 | Complete | Open Access |
040 | Aug - Sep '25 | Jul '25 | Sep '25 | Nov '25 | Jul '25 | |
041 | Titled | Achieved | Feb '25 | Feb '25 | Complete | Open Access |
042 | Feb - Mar '25 | Feb '25 | Apr '25 | Jun '25 | Jan '25 | Jan '25 |
043 | Mar - Apr '25 | Mar '25 | May '25 | Jul '25 | Mar '25 | Mar '25 |
Clementine, Upper Swan
Stage | Titles Due | PC Due | Water Access | Energisation Due | Pegging Due | Guided Access |
---|---|---|---|---|---|---|
004 | Mar - May '25 | Mar '25 | May '25 | Jul '25 | Mar '25 | Mar '25 |
005 | January '25 | Jan '25 | Mar '25 | May '25 | Dec '24 | Jan '25 |
08B | Titled | Achieved | Achieved | Achieved | Complete | Open Access |
09A | Titled | Achieved | Achieved | Feb '25 | Complete | Open Access |
10A | Titled | Achieved | Achieved | Mar '25 | Complete | Open Access |
Dalyellup Beach, Dalyellup
Stage | Titles Due | PC Due | Water Access | Energisation Due | Pegging Due | Guided Access |
---|---|---|---|---|---|---|
13C | Complete | |||||
13E | Titled | Jan '25 | Mar '25 | May '25 | Jan '25 | By Appointment |
18L | Titled | Feb '25 | Apr '25 | Jun '25 | Feb '25 | By Appointment |
Eden Beach, Jindalee
Stage | Titles Due | PC Due | Water Access | Energisation Due | Pegging Due | Guided Access |
---|---|---|---|---|---|---|
004 | Titled | Achieved | Achieved | Achieved | Complete | Open Access |
025 | Titled | Achieved | Achieved | Achieved | Complete | Open Access |
029 | Titled | Achieved | Achieved | Achieved | Complete | Open Access |
036 | March 2025 | Achieved | Feb '25 | Apr '25 | Dec '24 | Open Access |
Florence, Mandogalup
Stage | Titles Due | PC Due | Water Access | Energisation Due | Pegging Due | Guided Access |
---|---|---|---|---|---|---|
005 | Mar - May '25 | Jan '25 | Mar '25 | May '25 | Jan '25 | Jan '25 |
007 | June - July '25 | Achieved | Achieved | Achieved | Complete | Open Access |
03B | Titled | Achieved | Achieved | Achieved | Complete | Open Access |
06A | Mar - May '25 | Jan '25 | Mar '25 | May '25 | Jan '25 | Jan '25 |
06B | June - July '25 | Apr '25 | Jun '25 | Aug '25 | Apr '25 | Apr '25 |
Mahala, Forrestdale
Stage | Titles Due | PC Due | Water Access | Energisation Due | Pegging Due | Guided Access |
---|---|---|---|---|---|---|
006 | Apr - June 2025 | Apr '25 | Jun '25 | Aug '25 | Apr '25 | Apr '25 |
007 | July - Aug 2025 | Jul '25 | Sep '25 | Nov '25 | Jul '25 | Jun '25 |
008 | Titled | Achieved | Achieved | Achieved | Complete | Open Access |
010 | Titled | Achieved | Achieved | Achieved | Complete | Open Access |
013 | May 2025 | May '25 | Jul '25 | Sep '25 | May '25 | Apr '25 |
Myella, Wanneroo
Stage | Titles Due | PC Due | Water Access | Energisation Due | Pegging Due | Guided Access |
---|---|---|---|---|---|---|
001 | Titled | Achieved | Achieved | Achieved | Complete | Open Access |
Oakebella, Wellard
Stage | Titles Due | PC Due | Water Access | Energisation Due | Pegging Due | Guided Access |
---|---|---|---|---|---|---|
008 | Titled | Achieved | Jan '25 | Mar '25 | Complete | Open Access |
009 | June 2025 | May '25 | Jul '25 | Sep '25 | ||
014 | Apr - May '25 | Apr '25 | Jun '25 | Aug '25 | Apr '25 | Apr '25 |
08B | Titled | Achieved | Jan '25 | Mar '25 | Nov '24 | Open Access |
Ocean Hill, Lakelands
Stage | Titles Due | PC Due | Water Access | Energisation Due | Pegging Due | Guided Access |
---|---|---|---|---|---|---|
04A | Feb - Mar '25 | Achieved | Feb '25 | Apr '25 | Dec '24 | Open Access |
04B | Feb - Mar '25 | Achieved | Feb '25 | Apr '25 | Dec '24 | Open Access |
04C | Jan '25 | Achieved | Jan '25 | Mar '25 | Nov '24 | Open Access |
04D | Jan '25 | Achieved | Jan '25 | Mar '25 | Nov '24 | Open Access |
09B | Titled | Achieved | Achieved | Feb '25 | Complete | Open Access |
10A | July 2025 | May '25 | Jul '25 | Sep '25 | Jun '25 | Jun '25 |
Robinson Grove, Bellevue
Stage | Titles Due | PC Due | Water Access | Energisation Due | Pegging Due | Guided Access |
---|---|---|---|---|---|---|
001 | Titled | Achieved | Achieved | Achieved | Complete | Open Access |
002 | Titled | Achieved | Achieved | Achieved | Complete | |
004 | Aug - Spet '25 | Jul '25 | Aug '25 | Oct '25 | May '25 |
Seaside, Madora Bay
Stage | Titles Due | PC Due | Water Access | Energisation Due | Pegging Due | Guided Access |
---|---|---|---|---|---|---|
010 | Apr - Jun '25 | Mar '25 | May '25 | Jul '25 | Mar '25 | Mar '25 |
011 | Titled | Achieved | Achieved | Achieved | Complete | Open Access |
012 | Titled | Achieved | Jan '25 | Mar '25 | Nov '24 | Open Access |
013 | Titled | Jan '25 | Mar '25 | May '25 | Jan '25 | By Appointment |
015 | May - Jul '25 | Apr '25 | Jun '25 | Aug '25 | Apr '25 | Apr '24 |
016 | Aug - Sept '25 | Aug '25 | Oct '25 | Dec '25 | Jul '25 | Aug '25 |
025 | Titled | Achieved | Achieved | Feb '25 | Complete | Open Access |
The Glades, Byford
Stage | Titles Due | PC Due | Water Access | Energisation Due | Pegging Due | Guided Access |
---|---|---|---|---|---|---|
Beaufortia Retreat | ||||||
001 | February 2025 | Jan '25 | Mar '25 | May '25 | Jan '25 | Jan '25 |
Cardup Brook | ||||||
001 | May 2025 | Jun '25 | Aug '25 | Oct '25 | May '25 | May '25 |
002 | July - August 2025 | Jul '25 | Sep '25 | Nov '25 | Jul '25 | Jul '25 |
003 | Sep - Oct '25 | Sep '25 | Nov '25 | Jan '26 | Sep '25 | Sep '25 |
004 | Nov - Dec 2025 | Nov '25 | Jan '26 | Mar '26 | Nov '25 | Nov '25 |
Icaria | ||||||
013 | Titled | Achieved | Feb '25 | Apr '25 | Dec '24 | Nov '24 |
014 | February 2025 | Feb '25 | Apr '25 | Jun '25 | Feb '25 | Feb '25 |
Village Centre | ||||||
001 | Titled | Achieved | Achieved | Jan '25 | Complete | Open Access |
002 | Titled | Achieved | Achieved | Jan '25 | Complete | Open Access |
Trinity, Alkimos
Stage | Titles Due | PC Due | Water Access | Energisation Due | Pegging Due | Guided Access |
---|---|---|---|---|---|---|
Agora | ||||||
28C | Titled | Achieved | Achieved | Complete | ||
Atelier North | ||||||
004 | Sep - Oct '25 | Jul '25 | Sep '25 | Nov '25 | Jul '25 | |
Aura | ||||||
036 | Feb - Mar '25 | Feb '25 | Apr '25 | Jun '25 | Feb '25 | Feb '25 |
038 | June - July '25 | May '25 | Jul '25 | Sep '25 | May '25 | May '25 |
35C | Titled | Achieved | Achieved | Achieved | Complete | |
37A | Titled | Achieved | Achieved | Achieved | Complete | |
37B | Feb - Mar '25 | Mar '25 | May '25 | Jul '25 | Mar '25 | Feb '25 |
40B | Titled | Achieved | Nov '24 | Jan '25 | Complete |
Vertex, Yanchep
Stage | Titles Due | PC Due | Water Access | Energisation Due | Pegging Due | Guided Access |
---|---|---|---|---|---|---|
007 | Jan - Feb '25 | Achieved | Feb '25 | Apr '25 | Dec '24 | Open Access |
008 | February 2025 | Jan '25 | Mar '25 | May '25 | Dec '24 | |
05A | Titled | Achieved | Achieved | Achieved | Complete | |
05B | Titled | Achieved | Achieved | Achieved | Complete | |
05C | Titled | Achieved | Achieved | Achieved | Complete | |
06A | Titled | Achieved | Nov '24 | Jan '25 | ||
06B | Titled | Achieved | Nov '24 | Jan '25 | ||
06C | Titled | Achieved | Nov '24 | Jan '25 |
Disclaimer: Information provided is an indicative forecast as at the time of issue and may be subject to change.